Teck Announces Q1 & Covid-19 Update
- Apr
- 01
Teck Resources today provided an update on Q1 2020 operations, preventative measures taken with respect to COVID-19 and updated its 2020 annual guidance.
“Notwithstanding the challenges in the month of March related to COVID-19, all of our operations remain in production and our steelmaking coal results significantly exceeded guidance,” said Don Lindsay, President and CEO. “We remain focused on ensuring we have the necessary measures in place to safeguard the health and safety of our people and communities, while maintaining safe operations.”
Q1 2020 Operations Update
Following a difficult start to the year, results in our Steelmaking Coal Business Unit improved significantly in late February and March. First quarter steelmaking coal sales are estimated at 5.6 million tonnes, exceeding our guidance of 4.8 to 5.2 million tonnes. At the same time, based on preliminary results we expect to report adjusted site cost of sales of approximately $65 per tonne, well below previous expectations.
Finished coal inventories at our mine sites were reduced during the quarter, supporting sales and increasing operational flexibility.
In spite of a difficult start to the year, our steelmaking coal logistics supply chain performed well for the remainder of the quarter, with both CP and CN recovering from early weather-related disruptions and blockades. All three ports also performed well, in particular Westshore Terminals, which had a strong March.
Our Neptune facility upgrade continues to advance and major equipment deliveries are on track. We expect the new shiploader, stacker/reclaimer, and single dumper replacement to be commissioned around year-end. Completion of construction is still expected in Q1 2021, with the new double dumper expected to be commissioned in Q2 2021. The shutdown at our Elkview Operations to complete the plant expansion is also progressing well and we expect completion in mid-April. The Elkview plant is being expanded from a capacity of 7 million tonnes to 9 million tonnes, which will enable us to replace higher cost production from our Cardinal River Mine, which produced 1.4 million tonnes in 2019, with lower cost production from Elkview when Cardinal River closes later this year. Taking into account both the cost savings and the higher average pricing for Elkview coal, assuming US$150 benchmark coal pricing and current exchange rates, this should translate to an annual $110 million increase in EBITDA.
The ongoing impacts of the COVID-19 pandemic have the potential to affect both cost and schedule for these projects, and although impacts to date have not been material, we continue to monitor progress closely given the level of uncertainty.
As previously announced, construction at our Quebrada Blanca Phase 2 (QB2) project was temporarily suspended on March 18. All non-essential employees have been safely demobilized. At this time, construction remains suspended.
COVID-19 Response
Teck has implemented extensive preventative measures across all offices and operations in order to safeguard the health of our employees and local communities, while continuing to operate safely and responsibly maintain employment and economic activity. These measures include enhanced cleaning and disinfecting protocols, eliminating group meetings, reducing occupancy on crew buses, screening contractors and visitors, promoting preventative measures like hand washing, requiring employees returning from international travel or showing symptoms to self-isolate, and implementing remote work where possible.
As part of our focus on ensuring the health and safety of our employees and communities, we have also implemented a temporary slowdown of operations and reduction of crews by up to 50% of regular levels at our steelmaking coal and Highland Valley Copper operations. These measures commenced on March 25 and will be in place for an initial two week period, after which we will re-evaluate in light of the evolving situation. All employees available for work will continue to be paid as normal during the initial two-week period.
COVID-19 Production Impacts
Impacts from COVID-19 will vary by operation, but production will continue at sites on a reduced basis.
While the reductions at our steelmaking coal operations will vary by mine, total production is expected to be reduced on average to approximately 80% to 85% of normal levels during the initial two week period. During this period historically high mine site clean coal inventories are expected to be drawn down to support sales. At Highland Valley Copper, crew reductions are expected to reduce production to 80% to 85% of normal levels for the initial two week period.
At our Trail Operations we have temporarily reduced the number of employees on site by one third while continuing to operate at planned production levels. At Red Dog, production remains at planned levels despite the significant travel restrictions and modified schedules required to maintain safe operations due to the fly-in fly-out nature of the operation. In Peru, our Antamina mine continues to operate at full production levels with less than half of the normal workforce. At Carmen de Andacollo in Chile, full production has also been maintained to date with reduced workforce levels.
At our QB2 project, after the initial two-week suspension, project construction activities remain on hold. It is not currently possible to predict when construction activities will be re-started. For more information on the current status of QB2 please refer to our press release titled “Teck Announces Updated QB2 Capital Estimate” issued March 31, 2020.
We are continuing to work with our unions and affected communities and are following the guidance of government and public health authorities, and will adapt our response as necessary as this situation continues to evolve.
2020 Guidance
We have outlined above the immediate impact of these measures on expected production levels at our operations. We are still assessing longer term response actions, and our ability to maintain operations at current levels, or potentially to increase staffing levels and production. COVID-19 has the potential to affect both our customers and certain of our suppliers, and we are closely monitoring potential impacts on demand for our products, as well as our supply chain. Our operating plans will depend in part on regulatory restrictions that may affect our business, as well as the progress of the pandemic generally, and the extent of additional measures, if any, required to protect the health and safety of employees. The actual degree and duration of production slowdowns and/or staff reductions and related costs is unknown at this time. Given the high degree of uncertainty associated with the current COVID-19 situation we are suspending our 2020 guidance. We will provide a further update when we report our Q1 2020 financial results.
Recent Posts
- Alberta’s Highest Court Squeezes Alberta’s Coal Plans
- Province planning cleaner water in Elk Valley
- B.C. Fines Teck Coal Over $220K for Unauthorized Waste Spills
- Alberta Study Claims Mines Spreading Toxic Organic Contaminants
- Teck Named to 2024 Best 50 Corporate Citizens in Canada
Elk Valley Coal Links
- Centerpoint Resources Inc. A mine exploration and development company that owns Bingay Coal.
- City of Fernie The cultural and activity centre of the Elk Valley.
- Crowsnest Pass Coal Mining Ltd. Potential for a significant underground mine operation producing high quality coking coal.
- District of Elkford Founded in 1971 as a home for miners working at Fording Coal.
- District of Sparwood Sparwood, BC is yours and mine to discover!
- Elk River Alliance The Elk River Alliance has spent over a decade monitoring the Elk River Watershed
- Elk Valley Resources Elk Valley Resources (EVR) operates four steelmaking coal mines in the Elk Valley.
- Fernie.com Everything you need to know about Fernie BC.
- Glencore Owns a 77% interest in Elk Valley Resources.
- Grizzly Discoveries Grizzly is a Canadian exploration company exploring for gold and base metal deposits.
- Jameson Resources Ltd. Coal Mountain Coking Coal in Alexander Creek.
- Ktunaxa Nation Working together, managing our lands and resources, within a self-sufficient, self-governing Nation.
- Mining Association of British Columbia Represents the needs and interests of coal, metal, industrial mineral companies and smelters.
- Nippon Steel Japan’s largest steelmaker with a 20% interest in Elk Valley Resources.
- North Coal Ltd. Focused on the exploration and development of the Michel Creek Coking Coal Project.
- Pacific American Coal Ltd. Identified a 257 million tonne JORC resource at its Elko Coking Coal Project
- POSCO A South Korean steel-making company headquartered in Pohang with 3% interest in EVR.
- Teck Resources Ltd. Canada’s Largest Diversified Resource Company.
- United Steelworkers Local 9346 The Trade Union for the hourly employees at Teck Coal Ltd. – Elkview Operations
- Wildsight Working to protect wildlife, water and wild places in Canada’s Columbia and Rocky Mountain regions.